Old RR12 Bike / Pedestrian & Widening

Background & Schedule

    • 2017 - Project delayed at the request of City Council to make funds available for needed drainage projects
    • 2018 – Design Plans Completed
    • 2020-2022 – Project is on hold until the completion of Hopkins Street Improvements Project
    • Hopkins Street Improvements Project is using Old RR 12 as a major detour; both projects cannot be under construction at the same time
    • Construction is expected to be completed in late 2022
    • Hopkins Street Improvements Project Web page: Hopkins St Improvements - Bishop to Moore

Construction Schedule & Budget

  • 2023 - Start Construction
  • 2025 - End Construction
  • $6.6 M