Main Lift Station Force Main Replacement - March 2021

  • Storm Sewer: 50% complete along River Road with final completion scheduled after both proposed force mains are installed.
  • Force Mains:  90% complete; Force main line B will be installed up to the Wastewater Treatment Plant (WWPT) and then begin installing line A starting at the WWTP working back towards Cape Street.  Lift station tie-in is scheduled for late March.
  • Underground Bores: 12” reclaimed water bore is complete and the 24” force main bore under Cape Street is currently underway and nearing completion.
  • Reclaimed Water: Construction of the bulk filling station began in late January.  Anticipated completion is in April.

If you would like to receive project updates by email please send your email address to: enginfo@sanmarcostx.gov 